Adana Adıyaman Afyon Ağrı Aksaray Amasya Ankara Antalya Ardahan Artvin Aydın Balıkesir Bartın Batman Bayburt Bilecik Bingöl Bitlis Bolu Burdur Bursa Çanakkale Çankırı Çorum Denizli Diyarbakır Düzce Edirne Elazığ Erzincan Erzurum Eskişehir Gaziantep Giresun Gümüşhane Hakkari Hatay Iğdır Isparta İstanbul İzmir K.Maraş Karabük Karaman Kars Kastamonu Kayseri Kırıkkale Kırklareli Kırşehir Kilis Kocaeli Konya Kütahya Malatya Manisa Mardin Mersin Muğla Muş Nevşehir Niğde Ordu Osmaniye Rize Sakarya Samsun Siirt Sinop Sivas Şanlıurfa Şırnak Tekirdağ Tokat Trabzon Tunceli Uşak Van Yalova Yozgat Zonguldak
İstanbul
Az Bulutlu
16°C
İstanbul
16°C
Az Bulutlu
Pazartesi Yağmurlu
20°C
Salı Az Bulutlu
9°C
Çarşamba Parçalı Bulutlu
10°C
Perşembe Az Bulutlu
14°C

Yusufeli Dam turns four as electricity output reaches 5.6 billion kWh

Minister İbrahim Yumaklı said Yusufeli Dam and Hydroelectric Power Plant had generated 5.6 billion kilowatt-hours and contributed more than 16.7 billion lira to the economy. Electricity generation began in November 2023.

Yusufeli Dam turns four as electricity output reaches 5.6 billion kWh
23/11/2026 01:30
A+
A-

Agriculture and Forestry Minister İbrahim Yumaklı said Yusufeli Dam and Hydroelectric Power Plant, now four years old, had generated a total of 5.6 billion kilowatt-hours of electricity and contributed more than 16.7 billion lira to the economy. When assessing these totals for electricity generation in Türkiye, it is important to distinguish between the date the reservoir began filling and the start of power generation.

Key facts from the announcement

  • Yumaklı shared the electricity output and economic contribution figures on his NSosyal account.
  • The reservoir began filling on 22 November 2022.
  • Electricity generation began in November 2023, with full-capacity generation starting in March 2024.
  • With a structural height of 275 metres, Yusufeli was described as Türkiye’s tallest dam.

Does the fourth anniversary mean four full years of electricity generation?

No. The announcement describes the dam as four years old, but its timeline puts the start of electricity generation in November 2023. The reservoir began filling on 22 November 2022. The facility’s age therefore differs from the time it has spent generating electricity; the 5.6 billion kilowatt-hour total should not be read as four full years of output.

The third milestone was the start of full-capacity generation in March 2024. Reservoir filling, first electricity generation and reaching full capacity thus mark three distinct stages in bringing the facility into operation.

What does the economic contribution figure mean for the public?

The figure of more than 16.7 billion lira announced by Yumaklı is presented as the dam and power plant’s total contribution to the economy. Electricity output, meanwhile, is expressed in kilowatt-hours. One measures a monetary contribution and the other the amount of energy generated, so the two figures represent different measures.

Questions about Yusufeli Dam

Where does Yusufeli Dam rank worldwide?

According to the video in Yumaklı’s post, Yusufeli is the world’s fifth-tallest dam in its class. This is a ranking within its class, not an overall ranking covering all dams.

Which announcement are the generation figures based on?

The figures come from Agriculture and Forestry Minister İbrahim Yumaklı’s NSosyal post. An Anadolu Ajansı report published by Bigpara relays the minister’s statement and the information in the video accompanying his post.